There is a form used to document the completion of these procedures. The form includes a series of check boxes relating to each test or verification that needs to be performed. When completing the forms, check the appropriate box on the form after each test or verification is completed. Where the form includes data entry locations other than check boxes, enter the data requested on the form.
The form is located in Appendix A.
• NRCA-LTO-02-A Outdoor Motion Sensor and Lighting Shut-off Controls Acceptance Document
NRCA-LTO-02-A – Outdoor Lighting Acceptance Tests
Project Information
• PROJECT NAME is the title of the project, as shown on the Code Compliance forms.
• PROJECT ADDRESS is the address of the project as shown on the Code Compliance forms.
•ENFORCEMENT AGENCY identifies who has enforcement jurisdiction such as the county or city. The enforcement agency is the entity that issued the building permit
• PERMIT NUMBER is from the permit issued by the enforcement agency and is located on the building permit.
Construction Inspection (Pre-test Inspection)
This section consists of check boxes. Complete check boxes as instructed.
Functional Testing
This section requires data entry by following individual test procedures.
Certification Statement
The statement of compliance is signed by the person responsible for performing the test and verifying system performance. The signatory provides the following: name; company name; signature and date signed; as well as license number and expiration date.