13.38   Field Process

The construction inspection is the first step in performing the acceptance tests. In general, this inspection should identify:

      Fenestration products, HVAC equipment, and controls are properly specified, properly located, identified, correctly installed, calibrated and set points and schedules established.

      Documentation is available to identify settings and programs for each device, and

      For some air distribution systems (as identified in §110.6(a) and §140.4(l)), this may include select tests to verify acceptable leakage rates while access is available.

      Functional and Verification Testing is to be performed on the following devices:

Envelope

      ENV-1A – Will no longer be used. Required information has been transferred to NRCA-ENV-02-F.

      NRCA-ENV-02-F – Envelope components require NFRC or Energy Commissions Label Certificate including site-built fenestration. Label Certificate matches building plans and energy compliance documentation.

Mechanical

      MECH-1A – Will no longer be used. Required information has been transferred to MECH -2A and other Mechanical Acceptance forms.

      NRCA-MCH-02-A – Minimum ventilation controls for all constant and variable air volume systems.

      NRCA-MCH-03-A – Zone temperature and scheduling controls for all constant volume, single-zone, unitary air conditioner and heat pump systems.

      NRCA-MCH-04-A – Duct leakage on a subset of small single-zone systems depending on the ductwork location.

      NRCA-MCH-05-A – Air economizer controls for all economizers that are not factory installed and tested.

      NRCA-MCH-06-A – All demand-controlled ventilation control systems.

      NRCA-MCH-07-A – All supply fan variable flow controls.

      NRCA-MCH-08-A – Valve leakage for hydronic variable flow systems and isolation valves on chillers and boilers in plants with more than one chiller or boiler being served by the same primary pumps through a common header.

      NRCA-MCH-09-A – Supply water temperature reset control strategies programmed into the building automation system for any water systems (i.e. chilled, hot, or condenser water).

      NRCA-MCH-10-A – Hydronic variable flow controls on any water system where the pumps are controlled by variable frequency drives (i.e. chilled and hot water systems; water-loop heat pump systems).

      NRCA-MCH-11-A – Automatic Demand Shed Control.

      NRCA-MCH-12-A – Fault Detection & Diagnostics (FDD) for Packaged Direct Expansion Units.

      NRCA-MCH-13-A – Automatic Fault Detection and Diagnostic Systems (FDD) for Air Handling Units and Zone Terminal Units Acceptance

      NRCA-MCH-14-A – Distributed Energy Storage DX AC systems Acceptance

      NRCA-MCH-15-A – Thermal Energy Storage (TES) System Acceptance

      NRCA-MCH-16-A – Supply Air Temperature Reset Controls Acceptance

      NRCA-MCH-17-A – Condenser Water Supply Temperature Reset Controls Acceptance

      NRCA-MCH-18-A – Energy Management Control System Acceptance

Process

      NRCA-PRC-01-A – Compressed Air System Acceptance

      NRCA-PRC-02-A – Commercial Kitchen Exhaust System Acceptance

      NRCA-PRC-03-F – Enclosed Parking Garage Exhaust System Acceptance

      NRCA-PRC-04-A – Refrigerated Warehouse – Evaporator Fan Motor Controls Acceptance

      NRCA-PRC-05-A – Refrigerated Warehouse – Evaporative Condenser Controls Acceptance

      NRCA-PRC-06-A – Refrigerated Warehouse – Air-Cooled Condenser Controls Acceptance

      NRCA-PRC-07-A – Refrigerated Warehouse – Compressor Variable Speed Acceptance

      NRCA-PRC-08-A – Refrigerated Warehouse – Electric Resistance Underslab Heating System Acceptance