Administrative Requirements
The administrative requirements contained in the Standards require the lighting plans and specifications to contain:
Completed acceptance testing forms for automatic daylighting controls, manual daylight switching, occupant sensing devices and automatic shut-off controls.
Record drawings are provided to the building owners within 90 days of receiving a final occupancy permit.
Operating and maintenance information be provided to the building owner.
Requirement for the issuance of installation certificates for daylighting controls, occupant sensing devices and automatic shut-off controls.
Example:
The plans and specifications would require automatic shut-off lighting controls. A construction inspection would verify the device location and wiring is complete. Acceptance tests would verify proper zoning, on-off functions and overrides to assure the shut-off system is properly functioning. Owners’ manuals and maintenance information would be prepared for delivery to the building owner. Finally, record drawing information, including programming information for the automatic shut-off lighting controls must be submitted to the building owner within 90 days of the issuance of a final occupancy permit.