Construction Inspection
That the EMCS interface enable activation of the central demand shed controls.
Functional Testing
Step 1 Engage the global demand shed system.
• This can be done by either jumping the digital contact or simply overriding its condition in the EMCS front end. Wait 5-10 minutes to let the changes take effect.
Verify and Document
• That the cooling setpoints in the non-critical spaces increase by the proper amount.
• That the cooling setpoints in the critical spaces do not change.
Step 2 Disengage the global demand shed system.
• This can be done by either removing the jumper from the digital contact or simply releasing the override of the point in the EMCS front end. Wait 5-10 minutes to let the changes take effect.
Verify and Document
• That the cooling setpoints in the non-critical spaces return to their original setpoint.
• That the cooling setpoints in the critical spaces do not change.