13.86   Energy Management Control System Acceptance Test Procedure, Use Form NRCAMCH18A

Test Procedure

Construction Inspection

Ensure the following actions have been completed:

      Factory start-up and check-out complete        

      I/O point lists available          

      Point-to-point verification completed                                                  

      Sequence of operations of each system are programmed                   

      Written sequences are available                     

      Input sensors are calibrated               

Verification Checks

Conduct the following verification checks to validate the functionality of the EMCS:

      Verify the control graphics represent the system configuration

      Verify control points are properly mapped to the graphics screen

      Raise and lower a sampling of space temperature setpoints in the software and verify the system responds appropriately

      Verify the time-of-day start-up and shut-down function initiates a proper system response

      Verify trending capabilities by establishing trend logs for a sampling of control points

      Verify alarm conditions are monitored

      Verify the EMCS panel is installed on an emergency power circuit or has adequate battery back-up