Test Procedure
Construction Inspection
Ensure the following actions have been completed:
•Factory start-up and check-out complete
•I/O point lists available
•Point-to-point verification completed
•Sequence of operations of each system are programmed
•Written sequences are available
•Input sensors are calibrated
Verification Checks
Conduct the following verification checks to validate the functionality of the EMCS:
•Verify the control graphics represent the system configuration
•Verify control points are properly mapped to the graphics screen
•Raise and lower a sampling of space temperature setpoints in the software and verify the system responds appropriately
•Verify the time-of-day start-up and shut-down function initiates a proper system response
•Verify trending capabilities by establishing trend logs for a sampling of control points
•Verify alarm conditions are monitored
•Verify the EMCS panel is installed on an emergency power circuit or has adequate battery back-up