Test Procedure
Construction Inspection
Ensure the following actions have been completed:
• Factory start-up and check-out complete
• I/O point lists available
• Point-to-point verification completed
• Sequence of operations of each system are programmed
• Written sequences are available
• Input sensors are calibrated
Verification Checks
Conduct the following verification checks to validate the functionality of the EMCS:
• Verify the control graphics represent the system configuration
• Verify control points are properly mapped to the graphics screen
• Raise and lower a sampling of space temperature setpoints in the software and verify the system responds appropriately
• Verify the time-of-day start-up and shut-down function initiates a proper system response
• Verify trending capabilities by establishing trend logs for a sampling of control points
• Verify alarm conditions are monitored
• Verify the EMCS panel is installed on an emergency power circuit or has adequate battery back-up