SECTION 140.1 – PERFORMANCE APPROACH: ENERGY BUDGETS

NR-Manual-Button

A building complies with the performance approach if the energy budget calculated for the Proposed Design Building under Subsection (b) is no greater than the energy budget calculated for the Standard Design Building under Subsection (a).

(a)        Energy Budget for the Standard Design Building.     

The energy budget for a proposed building is determined by applying the mandatory and prescriptive requirements to the Proposed Design Building.  The energy budget is the sum of the TDV energy for space-conditioning, indoor lighting, mechanical ventilation, service water heating, and covered process loads.

(b)       Energy Budget for the Proposed Design Building.

The energy budget for a Proposed Design 'Building is determined by calculating the TDV energy for the Proposed Design Building.  The energy budget is the sum of the TDV energy for space-conditioning, indoor lighting, mechanical ventilation and service water heating and covered process loads.

(c)        Calculation of Energy Budget.  

The TDV energy for both the Standard Design Building and the Proposed Design 'Building shall be computed by Compliance Software certified for this use by the Commission.  The processes for Compliance Software approval by the Commission are documented in the Nonresidential ACM Approval 'Manual.