10.1    Introduction

This chapter of the Nonresidential Compliance Manual addresses covered processes for the 2022 Building Energy Efficiency Standards (Energy Codes) (§120.6 and §140.9).

10.1.1    Organization and Content

This chapter is organized as follows:

    10.1 —  Introduction to Covered Processes

    10.2 —  Enclosed Parking Garages

    10.3 —  Commercial Kitchens

    10.4 —  Computer Rooms

    10.5 —  Commercial Refrigeration

    10.6 —  Refrigerated Warehouses

    10.7 —  Laboratory Exhaust

    10.8 —  Compressed Air Systems

    10.9 —  Process Boilers

    10.10 —  Elevator Lighting and Ventilation Controls

    10.11 —  Escalators and Moving Walkways Speed Controls

    10.12 — Controlled Environment Horticulture

    10.13 — Steam Traps

10.1.2    Compliance Forms

Compliance documentation includes the certificates of compliance, reports, and other information that are submitted to the enforcement agency with an application for a building permit. Compliance documentation also includes documentation completed by the installing contractor, engineer/architect of record, or owner’s agent to verify that certain systems and equipment have been correctly installed and commissioned.

Under the prescriptive compliance approach, the project designer is responsible for completing the Process Compliance Forms & Worksheets. The project designer is required to complete all applicable sections of the NRCC-PRC-E. This form is required on plans for all submittals with covered processes. For the performance compliance approach this form will automatically be completed by the approved computer compliance program.

10.1.3    What Is New for the 2022 California Energy Code?

Significant changes for covered process in the 2022 update to the Energy Codes include both new processing loads being covered as well as additional requirements being applied to process loads that were covered by the energy code previously. 

Newly covered process loads include:

    Controlled environment horticulture (mandatory measures).

Electric lighting for growing plants now must have high photosynthetic photon efficacy (PPE), which is spectrum-efficient for growing plants, and must have dimming and timeclock controls.

Dehumidifiers must meet federal dehumidifier standards or recover at least 75 percent of the heat used for reheating.

Conditioned greenhouses must have at least two glazing layers.

    Steam traps (mandatory measures).

Steam trap monitoring system which provides status updates of steam trap fault detection sensors.

Steam traps must have an integral strainer and blow-off valves, or a strainer and blow-off valve must be installed within 3 feet upstream of the steam trap.

    Compressed air systems (mandatory measures).

Base-compressed air-system requirements on total horsepower of compressors connected to compressed air piping.

Energy and air demand monitoring systems capable of measuring and logging pressure, compressor power and compressor airflow of the compressed air systems.

Leak testing requirements for compressed air piping.

Compressed air system pipe sizing requirements to minimize frictional losses in the distribution system.

    Computer room (prescriptive measures).

Require minimum efficiencies for alternating current uninterruptible power supplies.

    Transcritical carbon dioxide (CO2) refrigeration systems in refrigerated warehouses (mandatory)

Minimum condensing temperature

Transcritical gas coolers — sizing requirements, minimum efficiency and air-cooled gas coolers prohibited in some climate zones

    Transcritical CO2 refrigeration systems in commercial refrigeration (mandatory)

Minimum condensing temperature

Transcritical gas coolers — sizing requirements, minimum efficiency  and air-cooled gas coolers prohibited in some climate zones

    Automatic door closers in refrigerated warehouses

Revisions to covered process loads previously regulated under the Energy Code:

    Computer room (mandatory measures).

Prohibit reheating and simultaneous heating and cooling.

Humidification shall be adiabatic.

Unitary air conditioners and chilled water fan systems shall be designed to vary the airflow rate as a function of actual load.

    Computer room (prescriptive measures).

Define supply air temperatures for air and water economizers.

For air economizers and water economizers, revise ambient air temperatures when full economizing occurs.

Require air containment for computer rooms with information technology equipment (ITE) of 10 kW or more.