The 2016 Navigator Ace tool provides a step-by-step guide to the 2016 Title 24, Part 6 compliance process.
Laid out in an easy-to-follow flowchart, each step in the process is described in detail for the responsible
party including links to resources, code language and tools to assist with compliance.
Get started by choosing Residential or Nonresidential, then Performance or Prescriptive path. Not
sure? We have guidance for that too!
Then you can click on each box to expand a print-ready PDF with all the details for that step or
download the entire set of steps as a single PDF using the “Download All” button that will appear at the bottom
of the page.
Performance Flowchart
Prescriptive Flowchart
I'm Not Sure
Design Team
Use compliance software to generate CF1R-PRF-01-E
Design Team
Upload CF1R-PRF-01-E is to HERS registry. *Exceptions may apply
Design Team
Incorporate registered CF1R form in construction documents for compliance verification.
Design Team
Submit construction documents, including CF1R forms, to building department for plan check.
Plans Examiner
Review CF1R-PRF-01-E and construction documents for compliance during plan check.
Design Team
Pick up plan check comments, make revisions, and resubmit to Building Department.
Plans Examiner
Issue permit once compliance is verified.
Contractor
Obtain copy of CF1R-PRF-01-E form with construction documents.
Contractor
Determine if HERS verification is needed & include costs in bid & time in schedule.
Contractor
Determine which CF2R/ CF3R forms to post, for verification and inspection.
Installer/Rater
Complete CF2R/CF3R forms (and registered if applicable).
Contractor
Have the registered (if applicable) CF2R/ CF3R forms complete and ready for inspector.
Inspector
Verify CF1R, CF2R, & CF3R forms in field and issue certificate of occupancy.
Contractor
Hand over document package to Owner
DOWNLOAD ALL
Design Team
Determine which Part 6 requirements and CF1R forms are applicable.
Design Team
Determine whether or not HERS verification is required.
Design Team
Complete CF1R forms obtained on CEC website, or within HERS registry (if HERS is applicable).
Design Team
Incorporate CF1R forms in construction documents for compliance verification.
Design Team
Submit construction documents including forms to Building Department for plan check.
Plans Examiner
Review CF1R forms and construction documents for compliance during plan check.
Design Team
Pick up plan check comments, make revisions, and resubmit toBuilding Department.
Plans Examiner
Issue permit once compliance is verified.
Contractor
Obtain copy of CF1R forms with construction documents.
Contractor
Determine if HERS verification is needed & include costs in bid & time in schedule.
Contractor
Determine which CF2R/ CF3R forms will be needed when inspector arrives.
Installer/Rater
Complete CF2R/CF3R forms (and register if applicable).
Contractor
Have the registered (if applicable) CF2R/ CF3R forms complete and ready for inspector.
Inspector
Verify CF1R, CF2R, & CF3R forms comply in field and issue certificate of occupancy.
Contractor
Hand over document package to Owner.
DOWNLOAD ALL
Design Team
Use compliance software to generate NRCC-PRF-01-E
Design Team
Coordinate and document design phase Commissioning activities. *Exceptions may apply
Design Team
Incorporate completed NRCC forms in construction documents for compliance verification.
Design Team
Submit construction documents including forms to Building Department for plan check.
Plans Examiner
Review NRCC forms and construction documents for compliance during plan check.
Design Team
Pick up plan check comments, make revisions, and resubmit to Building Department.
Plans Examiner
Issue permit once compliance is verified.
Contractor
Obtain copy of NRCC forms with construction documents.
Contractor
Determine if field commissioning is required and coordinates with the Cx Authority, and includes costs in bid as well as time in schedule.
Contractor
Determine if HERS verification or acceptance testing is needed & includes costs in bid & time in schedule.
Contractor
Determine & complete which NRCI/ NRCA/ NRCV forms to post, for verification and inspection.
Installer/Rater
Complete NRCI/ NRCA/ NRCV forms
Inspector
Determine which NRCI/ NRCA/ NRCV forms to look for at inspection.
Inspector
Verify NRCC/ NRCI/ NRCA/ NRCV forms in field and issues certificate of occupancy.
Contractor
Hand over document package to Owner
DOWNLOAD ALL
Design Team
Determine which Part 6 requirements and NRCC forms are applicable.
Design Team
Coordinate and document design phase Commissioning activities. *Exceptions may apply
Design Team
Complete appropriate NRCC forms & incorporate in construction documents for compliance verification.
Design Team
Submit construction documents including forms to Building Department for plan check.
Plans Examiner
Review NRCC forms and construction documents for compliance during plan check.
Design Team
Pick up plan check comments, make revisions, and resubmit to Building Department.
Plans Examiner
Issue permit once compliance is verified.
Contractor
Obtain copy of NRCC forms with construction documents.
Contractor
Determine if field commissioning is required and coordinates with the Cx Authority, and includes costs in bid as well as time in schedule.
Contractor
Determine if HERS verification or acceptance testing is needed & includes costs in bid & time in schedule.
Contractor
Determine & complete which NRCI/ NRCA/ NRCV forms to post, for verification and inspection.
Installer/Rater
Complete NRCI/ NRCA/ NRCV forms
Inspector
Determine which NRCI/ NRCA/ NRCV forms to look for at inspection.
Inspector
Verify NRCC/ NRCI/ NRCA/ NRCV forms in field and issues certificate of occupancy.
Contractor
Hand over document package to Owner
DOWNLOAD ALL