2019 Navigator Aceâ„¢
Please note: this tool is fully functional on mobile phones and tablets, however the layout will require extra
scrolling to move through the flowcharts and PDFs may be difficult to read. The best view of the flowcharts is
on a larger screen such as a tablet, laptop or desktop.
Also, the Download All button will download a zip file which most mobile phones are not able to open.
The 2019 Navigator Ace tool provides a step-by-step guide to the 2019 Title 24, Part 6 compliance process.
Laid out in an easy-to-follow flowchart, each step in the process is described in detail for the responsible
party including links to resources, code language and tools to assist with compliance.
Get started by choosing Residential or Nonresidential, then Performance or Prescriptive path. Not
sure? We have guidance for that too!
Then you can click on each box to expand a print-ready PDF with all the details for that step or
download the entire set of steps as a single PDF using the “Download All” button that will appear at the bottom
of the page.
Performance Flowchart
Prescriptive Flowchart
I'm Not Sure
Design Team
Use certified compliance software to generate the CF1R-PRF-01-E form.
Design Team
Upload the CF1R-PRF-01-E form to the HERS Registry. *Exceptions may apply.
Design Team
Incorporate registered CF1R forms in construction documents for compliance verification.
Design Team
Submit construction documents, including CF1R forms, to the building department for plan check.
Plans Examiner
Review the CF1R-PRF-01-E form and construction documents for compliance during the plan check.
Design Team
Pick up plan check comments, make revisions if necessary and resubmit to the building department.
Plans Examiner
Issue approval to commence construction after compliance is verified.
Contractor
Obtain a copy of the CF1R-PRF-01-E form with the construction documents.
Contractor
Determine if HERS verification is needed and include its costs in the bid and related time in the schedule.
Contractor
Determine which CF2R and CF3R forms will be needed when the inspector arrives.
Installer/ATT/ Rater
Complete and register the CF2R and CF3R forms, as applicable.
Contractor
As applicable, have the registered CF2R and CF3R forms complete and ready for the building inspector.
Inspector
In the field, verify that the CF1R, CF2R and CF3R forms comply and issue a certificate of occupancy.
Contractor
Give the document package to the building owner.
DOWNLOAD ALL
Design Team
Determine which Title 24, Part 6 requirements and CF1R forms are applicable.
Design Team
Determine if HERS verification is required.
Design Team
Complete and register the required CF1R forms as applicable.
Design Team
Incorporate the CF1R forms in the construction documents for compliance verification.
Design Team
Submit construction documents, including forms, to the building department for plan check.
Plans Examiner
Review the CF1R forms and construction documents for compliance during plan check.
Design Team
Pick up plan check comments, make revisions if necessary and resubmit to the building department.
Plans Examiner
Issue approval to commence construction after compliance is verified.
Contractor
Obtain a copy of the CF1R forms with the construction documents.
Contractor
Determine if HERS verification is needed and include its costs in the bid and related time in the schedule.
Contractor
Determine which CF2R and CF3R forms will be needed when the building inspector arrives.
Installer/ATT/ Rater
Complete and register the CF2R and CF3R forms, as applicable.
Contractor
As applicable, have the registered CF2R and CF3R forms complete and ready for the building inspector.
Inspector
In the field, verify that the CF1R, CF2R and CF3R forms will be needed and issue a certificate of occupancy.
Contractor
Give the document package to the building owner.
DOWNLOAD ALL
Design Team
Use compliance software to generate the NRCC-PRF-01-E form.
Design Team
Coordinate and document Design Phase Commissioning activities. *Exceptions may apply.
Design Team
Incorporate the completed NRCC forms into the construction documents for compliance verification.
Design Team
Submit the construction documents including the NRCC forms to the building department for plan check.
Plans Examiner
Review the NRCC forms and construction documents for compliance during plan check.
Design Team
Pick up plan check comments, make revisions and resubmit to Building Department.
Plans Examiner
Issue approval to commence construction after compliance is verified.
Contractor
Obtain a copy of the NRCC forms along with other construction documents.
Contractor
Determine if Commissioning (Cx) is required, coordinate with the Cx Authority and include Cx costs in the bid and related time in the schedule.
Contractor
Determine if HERS verification or Acceptance Testing is needed and include its costs in the bid and related time in the schedule.
Contractor
Determine which NRCI, NRCA, and/or NRCV forms are required for verification and inspection.
Installer/Rater
Complete the required NRCI, NRCA and NRCV forms.
Contractor
Collect the NRCI, NRCA and NRCV forms and have them ready for the inspector.
Inspector
Verify the NRCC, NRCI, NRCA and NRCV forms in the field and issue a certificate of occupancy.
Contractor
Give the document package to the building owner.
DOWNLOAD ALL
Design Team
Determine which Title 24, Part 6 requirements and NRCC forms are applicable.
Design Team
Coordinate and document Design Phase Commissioning activities. *Exceptions may apply.
Design Team
Complete the appropriate NRCC forms and incorporate in construction documents for compliance verification.
Design Team
Submit the construction documents, including the NRCC forms, to the building department for plan check.
Plans Examiner
Review the NRCC forms and construction documents for compliance during plan check.
Design Team
Pick up plan check comments, make revisions and resubmit to the building department.
Plans Examiner
Issue approval to commence construction after compliance is verified.
Contractor
Obtain a copy of the NRCC forms along with other construction documents.
Contractor
Determine if Commissioning (Cx) is required, coordinate with the Cx Authority and include Cx costs in the bid and related time in the schedule.
Contractor
Determine if HERS verification or Acceptance Testing is needed and include its costs in the bid and related time in the schedule.
Contractor
Determine which NRCI, NRCA and NRCV forms are required for verification and inspection.
Installer/Att/ Rater
Complete the required NRCI, NRCA and NRCV forms.
Contractor
Collect the NRCI, NRCA and NRCV forms and have them ready for the inspector.
Inspector
Verify the NRCC, NRCI, NRCA and NRCV forms in the field and issue a certificate of occupancy.
Contractor
Give the document package to the building owner.
DOWNLOAD ALL